The record
Written from the 1 report below. Nothing here is unsourced.
- The Mangaluru Water Metro project has reached a milestone by finalizing 11 out of 19 planned water transport terminals.
- These stations will link areas like the old port, Hoige Bazar, and Ullal through a dedicated water network.
- The initiative aims to alleviate road traffic congestion by utilizing the city's surrounding waterways for public transport.
- This infrastructure project is expected to boost local employment, trade, and tourism.
What to watch next
- Preparation of the Detailed Project Report (DPR)
- Finalization of terminal designs, ticket pricing, and fleet size
- Land acquisition process for the infrastructure
Who said what1
Only words found exactly in the article are shown, attributed and linked to the line they came from.
Shashidhar
Assistant Executive Engineer of the Port
1 quote · 1 outlet
“ವಾಟರ್ ಮೆಟ್ರೋ ಯೋಜನೆಯ ಆರಂಭಿಕ ವರದಿಯನ್ನು ಸರ್ಕಾರಕ್ಕೆ ಸಲ್ಲಿಸಲಾಗಿದೆ. ಒಟ್ಟು 19 ನಿಲ್ದಾಣಗಳನ್ನು ಗುರುತಿಸಲಾಗಿದ್ದು, ಸದ್ಯ 11 ನಿಲ್ದಾಣಗಳನ್ನು ಅಂತಿಮಗೊಳಿಸಲಾಗಿದೆ”
In the article
…ಇಲ್ಲದೆ ಜಲಮಾರ್ಗದ ಮೂಲಕ ಸುಲಭವಾಗಿ ನಗರದ ವಿವಿಧ ಭಾಗಗಳಿಗೆ ತಲುಪಬಹುದಾಗಿದೆ. ಯೋಜನೆಗೆ ಅಗತ್ಯವಿರುವ ಜಮೀನಿನ ಹಾಲಾಹಲ ಮಾಹಿತಿಯನ್ನು ಮೂಲಸೌಕರ್ಯ ಅಭಿವೃದ್ಧಿ ಇಲಾಖೆಗೆ ಈಗಾಗಲೇ ಸಲ್ಲಿಸಲಾಗಿದೆ. ಬಂದರು ಮತ್ತು ಮೀನುಗಾರಿಕೆ ಉಪವಿಭಾಗದ ಎಇಇ ಶಶಿಧರ್ ಮಾತನಾಡಿ, “ ವಾಟರ್ ಮೆಟ್ರೋ ಯೋಜನೆಯ ಆರಂಭಿಕ ವರದಿಯನ್ನು ಸರ್ಕಾರಕ್ಕೆ ಸಲ್ಲಿಸಲಾಗಿದೆ. ಒಟ್ಟು 19 ನಿಲ್ದಾಣಗಳನ್ನು ಗುರುತಿಸಲಾಗಿದ್ದು, ಸದ್ಯ 11 ನಿಲ್ದಾಣಗಳನ್ನು ಅಂತಿಮಗೊಳಿಸಲಾಗಿದೆ ” ಎಂದಿದ್ದಾರೆ. ಮುಂದಿನ ಹಂತದಲ್ಲಿ ವಿಸ್ತೃತ ಯೋಜನಾ ವರದಿ (DPR) ಸಿದ್ಧವಾಗಲಿದ್ದು, ಪ್ರತಿಯೊಂದು ನಿಲ್ದಾಣದ ವಿನ್ಯಾಸ, ನಿಖರ ಮಾರ್ಗ, ಟಿಕೆಟ್ ದರ, ಬೋಟ್ಗಳ ಸಂಖ್ಯೆ, ಪ್ರಯಾಣದ ಸಮಯ ಹಾಗೂ ಅಂತಿಮ ಜಾಗದ ವಿವರಗಳನ್ನು ನಿಗದಿಪಡಿಸಲಾಗುವುದು. ರಾಜ್ಯದ ಸುದ್ದಿಗಳನ್ನು…
Coverage1
All filed from India
Named India · Infrastructure Development Department · Mangaluru · Mangaluru Port and Fisheries Sub-Division · Shashidhar
The 1 report is listed beside the record.