Mumbai-Goa Highway cost jumps 48% to Rs 16,909cr

Headline by Prism · from 1 report

The cost of the Mumbai-Goa highway expansion project has increased by 48% to Rs 16,909 crore, with ongoing delays impacting commuters.

1 outlet · 1 report · EnglishOne source so far

The record

Written from the 1 report below. Nothing here is unsourced.

  • The four-laning project for the Mumbai-Goa highway has seen costs rise significantly to Rs 16,909 crore, exceeding original estimates while the road remains incomplete after years of work.
  • Delays are attributed by officials to land acquisition challenges, pre-construction activities, and contractor financial issues.
  • These persistent setbacks continue to cause traffic congestion and hardship for commuters traveling between Mumbai and the Konkan region.

What to watch next

  • Completion of the final 20km stretch originally targeted for June 2026
  • Government accountability and responses regarding project management
  • Impact of future construction on traffic during peak travel seasons

Who said what1

Only words found exactly in the article are shown, attributed and linked to the line they came from.

Jeetendra Ghadge

1 quote · 1 outlet

  • When a project of this scale has remained incomplete for nearly 15 years despite thousands of crores being sanctioned and spent, the government must answer a basic question: who is ultimately accountable for the delay?
    [1]The Times of India — Mumbai2h agoOpen at the quote ↗
    In the article

    by the RTI are being executed through the state PWD under the national highway programme. Earlier MoRTH records have also identified Maharashtra PWD as the executing agency for the Indapur-Zarap four-laning packages. “ When a project of this scale has remained incomplete for nearly 15 years despite thousands of crores being sanctioned and spent, the government must answer a basic question: who is ultimately accountable for the delay? ” Ghadge said. He also alleged that the prolonged delays had imposed a continuing human and economic cost on Konkan residents and travellers. The impact becomes particularly visible around Ganeshotsav, when lakhs of

Coverage1

1 report
English national1

All filed from India

Named India · IN-MH · Bombay High Court · Jeetendra Ghadge · Ministry of Road Transport and Highways · National Highways Authority of India · Nitin Gadkari · Public Works Department · The Young Whistleblowers Foundation