Written from the 1 report below. Nothing here is unsourced.
- The MMRDA has started appointing a consultant and preparing bid documents for the 11.83-km Metro Line 5A extension from Durgadi in Kalyan to Ulhasnagar, following state approval of the revised project report in April 2026.
- The estimated Rs 4,063 crore extension will link Ulhasnagar to the under-construction Metro Line 5 (Thane-Bhiwandi-Kalyan), improving connectivity for commuters in Kalyan and Ulhasnagar.
- The update was shared in an MMRDA letter to BJP MLA Kumar Ailani, who had sought a status report.
- The project has entered the pre-construction stage, though construction can begin only after the metro alignment is notified by the Union ministry.
What to watch next
- Notification of the metro alignment by the Union Ministry of Housing and Urban Affairs
- Appointment of the consultant through the tendering process
- Finalisation and award of civil construction bids
Coverage1
1 report
English national1
All filed from India
Named India · Bhiwandi · Durgadi · Kalyan · Metro Line 12 · Metro Line 4 · Metro Line 5 · Mumbai · Thane · Ulhasnagar · Bharatiya Janata Party (BJP) · Kumar Ailani · Maharashtra Urban Development Department
The 1 report is listed beside the record.
Ask this story
Answers cite the reports above, or say they can't.